Allowances, Exclusions and Change Orders: The Fine Print in a Remodel Bid

Most homeowners read a remodel bid from the top to the total. The parts that decide what you actually end up paying are usually further down, in the allowances, the exclusions and the change-order terms.

I've been in remodeling since 1999. I ran my own custom cabinet company building high-end kitchens, and for the last 11 years I've worked as a project manager, head carpenter and estimator. I've written this fine print, and I've managed jobs where it mattered. Here's what each piece means and what to ask about it.


Part 1: Allowances

What an allowance is

An allowance is a placeholder amount in the bid for something you haven't picked yet. Common allowances in remodels:

The bid says something like "Tile allowance: $X." When you pick your tile, if it costs less you get a credit, and if it costs more you pay the difference.

Why allowances exist

Allowances let a contractor give you a price before every selection is made. That's useful. Most people don't pick every faucet before they get bids.

How allowances go wrong

Questions to ask about allowances

  1. What does each allowance realistically buy? Can you show me an example product at that price?
  2. Does the allowance cover material only, or material and installation?
  3. If I go over, how is the difference charged? Is there a markup?
  4. If I come in under, do I get a credit?
  5. When do my selections need to be made?

Tip: when comparing bids, set every bid's allowances to the same realistic number. Otherwise you're comparing guesses, not prices.


Part 2: Exclusions

What an exclusion is

An exclusion is something the contractor is telling you is not in the price. Exclusions may be listed plainly ("Excludes: painting, appliance installation, permits") or tucked into general terms near the end of the bid.

Common remodel exclusions

Why exclusions are a good sign

A clear exclusions list is a sign of an honest bid. It tells you where the contractor's price stops. A bid with no exclusions isn't necessarily all-inclusive. It may just be vague.

How exclusions go wrong

Questions to ask about exclusions

  1. What's excluded from this price?
  2. For each exclusion, who's expected to handle it: me, another trade, or you as a change order?
  3. How do you handle hidden conditions once walls or floors are opened?
  4. If something excluded turns out to be needed, how will it be priced?

Part 3: Change orders

What a change order is

A change order is a written agreement to change the scope, price or schedule after the contract is signed. Changes happen for three main reasons:

  1. You change your mind, like a different tile, an added outlet or a moved light.
  2. Hidden conditions show up, like rot under the floor or wiring that isn't up to code.
  3. Something was missed in the original scope.

Changes are normal in remodeling. Problems come from changes that aren't written down.

What good change-order terms say

How change orders go wrong

Questions to ask about change orders

  1. How do you handle changes? Is everything in writing before the work?
  2. How are changes priced: fixed price, or time and materials? What's the markup?
  3. How will changes affect the schedule?
  4. When are change orders paid?
  5. Can I see a sample change-order form?

Where the fine print hides

These terms aren't always labeled clearly. When I read a bid, I check a few places:

Read the whole document, including attachments, before you compare totals. It's a few extra minutes that can save a lot of surprises later.

How the three fit together

Allowances, exclusions and change orders are connected:

That's why I read these three sections together when I review a bid. A bid with realistic allowances, a clear exclusions list and written change-order terms is usually a bid you can trust. It may not be the cheapest on paper, but it's less likely to surprise you.

A quick checklist before you sign

If you can't check every box, ask your contractor before you sign. For legal questions about your contract, talk to a licensed attorney in your state.

The bottom line

The total at the bottom of a bid is only as good as the fine print above it. Realistic allowances, clear exclusions and written change-order terms are what turn a bid's price into the price you'll actually pay.


Want help reading the fine print?

I offer remote bid reviews: a 45-minute Cal Video call with a written summary, or a written-only review. I'll go through your bid's allowances, exclusions and change-order terms and give you the questions to ask. It's advice only, not legal advice, and you make the decisions.

See the bid review options →

Not available for projects in Lucas, Wood or Fulton County, Ohio.

— Jeremy Skadeland, Field Soft Picks

General information only, not professional, legal or financial advice.